“Day 34 To Day 49”
Cypress Log Home Construction
Day 34- Roofing, Window & Door Delivery
Day 35- Working on roof and setting porch post and header beams
Day 36- Finish decking T&g on porch roofs
October 13th, Wednesday
Day 36 – Log Home Builder working on covered porch roof.
Day 37- Install roofing membrane, now Log Home roof is safe and dry
Day 38- Plumbing Rough-in starting
Day 39-40- Log home interior framing
October 16th, Saturday
Day 39 – Crew working on interior wall framing. Plumbers onsite working on rough in.
Day 40 – October 17th, 2010 Sunday – No Work
Day 41- Log Home Window & door Bucking Install
October 18th, Monday
Day 41 – Log Crew working on window and door bucking and front covered porch system. Plumber onsite working on rough in.
Day 42 Window & Door bucking and framing on custom bay window
Day 43- Setting log home Door and windows
Day 44-46- Misc Items, Bay window framing
October 21th, Thursday
Day 44 – Log Crew framing 6/0 x 6/10 doors. Completing log to roof transition. Framing bay window.
October 22nd, Friday
Day 45 – Log Home Crew working on misc. items, HVAC crew onsite, met with the owner and laid out all vents/returns and installed ductwork.
October 23rd, Saturday
Day 46 – Log Crew working on misc. items
Day 47-48 Metal roof measurements, plumbing, all roof penetrations
October 24th, Sunday
Day 47 – No Work
October 25th, Monday
Day 48 – Log Home Building Crew working on misc. items, drop ceilings, elect. cutouts, finished sheathing bay window and set both 6/0 x 6/10 exterior doors. H.V.A.C crew onsite, met with owner and laid out last 2 vents that were in conflict with floor structural members. “H.V.A.C rough-in complete.” Plumbers onsite, set tub and finishing rough-in. Metal roof contractor onsite taking finish roof measurements and ordered metal to be delivered tomorrow. Coordinated and completed all roof penetrations with roofing contractor (H.V.A.C, Plumbing, and Gas) Metal roof installation scheduled to start Wednesday.